The Elliot Ditch Constructed Wetlands
The Elliot Ditch Constructed Wetlands
PE, CPESC Email aaron.zambo@hdrinc.com
Page Range: 79 – 87
DOI: 10.3992/jgb.2.3.79
The purpose of this experiment was to determine the contaminant load reduction incurred using a constructed wetland with an average hydraulic detention time of five days in treating agricultural runoff. The main contaminants present in the runoff were nitrogen and phosphorus from agricultural fertilizers. The findings of the experiment show that significant contaminant load reduction results can be achieved with a detention time, of as little as five days, in a properly constructed wetland system.Abstract
Copyright: © College Publishing 2007